QUESTION 56

- (Topic 3)
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

Correct Answer: A

QUESTION 57

- (Topic 2)
At the start of a typical project life cycle, costs are:

Correct Answer: A

QUESTION 58

- (Topic 1)
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Correct Answer: A

QUESTION 59

- (Topic 2)
A project manager should communicate to stakeholders about resolved project issues by updating the:

Correct Answer: C

QUESTION 60

- (Topic 3)
Which is one of the major outputs of Sequence Activities?

Correct Answer: C