QUESTION 51

- (Topic 5)
Which of the following is a tool and technique used to monitor risk?

Correct Answer: A

QUESTION 52

- (Topic 2)
A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Correct Answer: A

QUESTION 53

- (Topic 1)
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Correct Answer: D

QUESTION 54

- (Topic 2)
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Correct Answer: A

QUESTION 55

- (Topic 2)
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

Correct Answer: C