- (Topic 2)
The following is a network diagram for a project.
The free float for Activity E is how many days?
Correct Answer:
C
- (Topic 1)
Enterprise environmental factors are an input to which process?
Correct Answer:
C
- (Topic 2)
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
Correct Answer:
A
- (Topic 5)
The staffing management plan is part of the:
Correct Answer:
C
- (Topic 3)
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
Correct Answer:
A