QUESTION 1

- (Topic 2)
The following is a network diagram for a project.
PMI-100 dumps exhibit
The free float for Activity E is how many days?

Correct Answer: C

QUESTION 2

- (Topic 1)
Enterprise environmental factors are an input to which process?

Correct Answer: C

QUESTION 3

- (Topic 2)
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Correct Answer: A

QUESTION 4

- (Topic 5)
The staffing management plan is part of the:

Correct Answer: C

QUESTION 5

- (Topic 3)
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

Correct Answer: A