QUESTION 16

A car company authorized a project to build more fuel-efficient cars in response to gasoline shortages. With which of the following strategic considerations was this project mainly concerned?

Correct Answer: A

QUESTION 17

To which process is work performance information an input?

Correct Answer: A

QUESTION 18

Requirements documentation will typically contain at least:

Correct Answer: D

QUESTION 19

The project charter is an input to which process?

Correct Answer: B

QUESTION 20

A tool or technique used in the Control Procurements process is:

Correct Answer: B