QUESTION 11

Design of experiments (DOE) should be used during which of the following processes?

Correct Answer: B

QUESTION 12

A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

Correct Answer: C

QUESTION 13

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Correct Answer: A

QUESTION 14

Which is an input to the Scope Verification Process?

Correct Answer: D

QUESTION 15

An input to the Manage Project Team process is:

Correct Answer: A