QUESTION 41

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Correct Answer: B
The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.

QUESTION 42

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).

Correct Answer: EF
During the project closure phase in the waterfall methodology, it is crucial to validate the deliverables to ensure that all project requirements have been met and the project outputs are complete and satisfactory. Additionally, reconciling the project budget is performed to ensure all financial records are accurate and reflect the actual project costs, which is essential for the formal closing of the project.
References = CompTIA Project+ Certification Study Guide (PK0-005)

QUESTION 43

Which of the following tools is best to use when conducting project meetings across time zones?

Correct Answer: C
Videoconference is the best tool to use when conducting project meetings across time zones, as it allows real-time communication, visual cues, screen sharing, and collaboration among the participants. Videoconference can also help build rapport and trust among the team members, and reduce the risk of misunderstandings or miscommunication. Videoconference tools such as Zoom, Skype, or Google Meet can also accommodate different time zones by showing the local time of each participant and allowing them to schedule meetings in advance12.

QUESTION 44

Which of the following contract types in project procurement has the highest risk for the buyer?

Correct Answer: B
A cost-plus contract is a type of contract where the buyer agrees to reimburse the seller for the actual costs of the work plus a fee, which can be fixed, percentage, incentive, or award based. This type of contract has the highest risk for the buyer because the buyer has no control over the cost or quantity of the work and the seller has little incentive to control the costs or complete the work efficiently. The seller may inflate the costs or prolong the work to increase the fee. The buyer may end up paying much more than the estimated budget or the market value of the work. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 9: Project Procurement Management; CompTIA Project+ Certification Exam Objectives, Domain 3: Project Execution, Objective 3.3: Execute procurement activities.

QUESTION 45

A team member identifies a critical issue in production. Which of the following should the project manager apply?

Correct Answer: C
A rollback plan, also known as a backout plan, is a strategy designed to reverse changes made during a project in case of failure or undesired results1. A rollback plan is a form of risk response that allows the project to restore the previous state and minimize the impact of the issue. A rollback plan is usually created during the planning phase and implemented during the execution or closing phase of the project. The other options are not correct because:
✑ A compliance check is a process that ensures that the project meets the relevant standards, regulations, and requirements. A compliance check is not a risk response, but rather a quality control or assurance activity.
✑ A release plan is a document that outlines the scope, schedule, and resources for delivering a product or service to the customer. A release plan is not a risk response, but rather a communication or scope management tool.
✑ A validation check is a process that verifies that the project deliverables meet the customer’s needs and expectations. A validation check is not a risk response, but rather a quality control or assurance activity. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, page 314; CompTIA Project+ Certification Exam Objectives, Domain 3: Project Execution, Objective 3.2: Given a scenario, execute and monitor project tasks using traditional methodologies; Backout Plan - DevX