QUESTION 31

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

Correct Answer: D
The SOW (statement of work) is a document that defines the scope, deliverables, schedule, and resources of a project. It is a contractual agreement between the buyer and the seller that should be changed first when there are approved changes to the product. Changing the SOW will ensure that the project expectations and requirements are updated and aligned with the customer’s requests. The other options are not documents that need to be changed first, but rather metrics or tools that can be used to measure or manage the project. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 3: Initiating Projects; CompTIA Project+ Certification Exam Objectives, Domain 2: Project Planning, Objective 2.1: Develop a project scope document.

QUESTION 32

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

Correct Answer: B
A project evaluation review is a tool that helps a project manager assess the activities performed, work effort applied, and the productivity of a project. It involves collecting and analyzing data on the project’s performance, outcomes, and impacts. It also provides feedback and recommendations for improvement and learning. A project evaluation review can be done at different stages of the project life cycle, such as during or after completion. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Project Evaluation and Assessment; CompTIA Project+ Certification Exam Objectives, Domain 4: Project Closure, Objective 4.1: Conduct project closure activities.

QUESTION 33

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Correct Answer: C
A weak matrix organizational structure is one where the project manager has low authority and the functional manager has high authority. The project manager is considered to be a coordinator or an escalator, and the team members are primarily loyal to their functional units. This can cause issues with team motivation, communication, and performance1

QUESTION 34

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Correct Answer: B
The waterfall methodology is a project management framework that follows a linear and sequential process, where each stage of the project must be completed before moving on to the next one. The stages of the waterfall model are initiation, planning, execution, and closure, as described in the question12.

QUESTION 35

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Correct Answer: CE
Issue log and change log are documents that should be used to record the event where the project team has just experienced an unexpected event and implemented a work-around. An issue log is a document that tracks and records any issues or problems that arise during a project and how they are resolved. An issue log can help to monitor and control the project performance and quality and prevent any negative impacts on the project objectives and deliverables. A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. A change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.