QUESTION 116

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

Correct Answer: C
The environmental factor would be impacted the most by requirements for a project to implement an air quality control system at a coal plant. This is because coal combustion produces various air pollutants, such as particulate matter (PM), sulfur dioxide (SO2), nitrogen oxides (NOx), carbon dioxide (CO2), and mercury, that can harm human health and the environment12. An air quality control system can reduce the emissions of these pollutants by using different technologies, such as low NOx burners, flue gas desulfurization, electrostatic precipitators, and carbon capture and storage23. However, these technologies also have environmental impacts, such as water consumption, waste generation, energy consumption, and greenhouse gas emissions4. Therefore, the project manager should consider the environmental factor in terms of the project scope, objectives, constraints, risks, and stakeholders, and evaluate the trade-offs and benefits of different air quality control options5. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 3: Project Scope Management, p. 97; Update on air pollution control strategies for coal-fired power plants; AQCS Air Quality Control Systems; NOx control for high-ash coal-fired power plants in India; Coal Dust Control

QUESTION 117

Which of the following software programs would be best to use to store information related to business transactions?

Correct Answer: C
Enterprise resource planning (ERP) software is a type of software that integrates various business functions and processes, such as accounting, finance, inventory, sales, purchasing, human resources, and more. ERP software helps businesses store, organize, and manage information related to business transactions, such as invoices, payments, orders, receipts, and reports. ERP software also provides real-time data analysis, reporting, and forecasting capabilities12.

QUESTION 118

A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?

Correct Answer: D
A gate review is a type of meeting that evaluates the completion and quality of a project stage and decides whether the project can proceed to the next stage. A gate review is a formal governance step that involves reviewing the goals, progress, risks, deliverables, and benefits of the project, and discussing if the project is still aligned with the business strategy and stakeholder expectations. A gate review can have different outcomes, such as go, kill, hold, recycle, or conditional go, depending on the assessment of the project status and viability123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; Everything Project Managers Need To Know About Gate Reviews | monday.com Blog; Gate reviews: What to do and why you need them - Rebel’s Guide to Project Management; Gates and How to Operate Them - GenSight

QUESTION 119

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Correct Answer: EF
Review the resource pool and review the project objectives are activities that the project manager should undertake after accepting a new project. Reviewing the resource pool involves identifying and evaluating the availability, skills, and competencies of the human and material resources that are needed for the project. Reviewing the project objectives involves understanding and clarifying the expected outcomes and benefits of the project and how they align with the organizational strategy and stakeholder expectations. These activities can help to plan and execute the project effectively and efficiently.

QUESTION 120

Which of the following tools is best to use when conducting project meetings across time zones?

Correct Answer: C
Videoconference is the best tool to use when conducting project meetings across time zones, as it allows real-time communication, visual cues, screen sharing, and collaboration among the participants. Videoconference can also help build rapport and trust among the team members, and reduce the risk of misunderstandings or miscommunication. Videoconference tools such as Zoom, Skype, or Google Meet can also accommodate different time zones by showing the local time of each participant and allowing them to schedule meetings in advance12.