During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?
Correct Answer:
C
A burndown chart is a visual representation of the remaining work versus the time required to complete it1. It is commonly used by agile teams to track the progress of each iteration or sprint and to forecast the project completion date2. A burndown chart shows the ideal work remaining line and the actual work remaining line, which can help the team identify any deviations or impediments and adjust accordingly1. A burndown chart is different from a Pareto chart, which shows the frequency of different causes of problems; a milestone chart, which shows the key events and deliverables of a project; and a Gantt chart, which shows the dependencies and durations of tasks in a project3. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 6: Planning Projects Part 2, page 173; Burndown Chart: What Is It & How to Use One for Agile - ProjectManager, Introduction and Components of a Burndown Chart sections; Burndown Chart: What it is, How to Use it, Example [2023] • Asana, Introduction and What is a burndown chart? sections.
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Correct Answer:
A
Avoiding is a conflict resolution technique that involves postponing or withdrawing from a conflict situation. The project manager is using this technique by taking a break and continuing the meeting on another day, hoping that the conflict will resolve itself or become less important over time. This technique may be appropriate when the conflict is trivial, the potential damage is greater than the benefits, or more information is needed before making a decision. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, page 287; [CompTIA Project+ Certification Exam Objectives], Domain 3: Project Execution, Objective 3.2: Given a scenario, apply appropriate conflict resolution techniques.
Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
Correct Answer:
D
This answer is based on the best practice of conflict resolution in project management, which is to use a collaborative or problem-solving approach that seeks a win- win outcome for all parties involved12. By facilitating a meeting, the project manager can help the team members communicate effectively, understand each other’s perspectives, and find a mutually acceptable solution that meets the project requirements. This way, the project manager can also maintain team morale and cohesion, and avoid imposing a decision that may cause resentment or dissatisfaction among the team members3. References = CompTIA Project+ Certification Study Guide4, CompTIA Project+ Certification Exam Objectives5, How Do You Handle Conflict in Project Management?1, 7 Strategies for Conflict Resolution in Project Management2, The Conflict Resolution Skills Every Project Manager Needs3
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
Correct Answer:
B
According to A Guide To Schedule Updating in Project Management, one of the best practices for effective schedule updating is to perform an impact analysis before making any changes to the schedule. An impact analysis helps the project manager to assess the effects of the change on the project scope, cost, quality, risk, and stakeholder expectations. It also helps to identify the best options for resolving the issue and minimizing the negative impacts. By performing an impact analysis first, the project manager can make informed decisions and communicate them clearly to the project team and stakeholders.
A project manager buys an extended warranty for a set of servers. Which of the following risk management strategies is the manager using?
Correct Answer:
A
Transfer is a risk management strategy that involves shifting the responsibility or impact of a risk to a third party, such as an insurance company, a vendor, or a contractor1. By buying an extended warranty for a set of servers, the project manager is transferring the risk of server failure or malfunction to the warranty provider, who will cover the cost of repair or replacement in case of a risk event. This way, the project manager reduces the exposure and liability of the project to the risk, while still retaining
some level of accountability and oversight2. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 8: Planning Projects Part 4, page 245; 4 Risk Management Strategies for Successful Project Execution, Risk transferring section; How to Manage Project Risk: A 5-Step Guide, Risk treatment section.