PK0-005 Dumps

PK0-005 Free Practice Test

CompTIA PK0-005: CompTIA Project+ Certification Exam

QUESTION 46

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

Correct Answer: C
An issue log is a document that records and tracks any issues that arise during a project and how they are resolved1. It is different from a risk register, which records and tracks potential risks that may or may not occur during a project2. When a risk becomes an issue, it means that it has occurred and has a negative impact on the project. Therefore, the project manager should update the issue log next to document the compliance issue, its cause, its impact, its priority, its owner, and its resolution status3. Updating the issue log will help the project manager communicate the issue to the stakeholders, monitor the progress of the mitigation plan, and prevent similar issues from happening again4. References = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 11: Executing Projects Part 2, page 331; Project Risk Mitigation Guide + Starter Kit | Smartsheet, Risk Register section; How to Make a Risk Management Plan (Template Included) - ProjectManager, Risk Register section; Issue Log - Project Management Knowledge, Introduction section; Issue Log Template: Free Download | ProjectManager, Introduction and How to Use an Issue Log sections.

QUESTION 47

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Correct Answer: B
Limiting access to members of the project team is a way to minimize the risk of compromising the project details if a cloud service is used. This means that only authorized and trusted individuals can access, view, modify, or share the project information stored in the cloud. Limiting access can prevent unauthorized access, data leakage, cyberattacks, or espionage from external parties who might want to steal or sabotage the new technology. Limiting access can also reduce the risk of human error, negligence, or misconduct from internal parties who might accidentally or intentionally expose or misuse the project information123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 4: Project Communications, p. 143; Cloud Security Risks and How to Mitigate Them | Cloud Academy; Cloud Security: How to Secure Your Data in the Cloud | Kaspersky; Cloud Security: Best Practices for Securing Cloud Computing | Cloud Security Alliance

QUESTION 48

Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

Correct Answer: C
The environmental factor would be impacted the most by requirements for a project to implement an air quality control system at a coal plant. This is because coal combustion produces various air pollutants, such as particulate matter (PM), sulfur dioxide (SO2), nitrogen oxides (NOx), carbon dioxide (CO2), and mercury, that can harm human health and the environment12. An air quality control system can reduce the emissions of these pollutants by using different technologies, such as low NOx burners, flue gas desulfurization, electrostatic precipitators, and carbon capture and storage23. However, these technologies also have environmental impacts, such as water consumption, waste generation, energy consumption, and greenhouse gas emissions4. Therefore, the project manager should consider the environmental factor in terms of the project scope, objectives, constraints, risks, and stakeholders, and evaluate the trade-offs and benefits of different air quality control options5. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 3: Project Scope Management, p. 97; Update on air pollution control strategies for coal-fired power plants; AQCS Air Quality Control Systems; NOx control for high-ash coal-fired power plants in India; Coal Dust Control

QUESTION 49

Which of the following software programs would be best to use to store information related to business transactions?

Correct Answer: C
Enterprise resource planning (ERP) software is a type of software that integrates various business functions and processes, such as accounting, finance, inventory, sales, purchasing, human resources, and more. ERP software helps businesses store, organize, and manage information related to business transactions, such as invoices, payments, orders, receipts, and reports. ERP software also provides real-time data analysis, reporting, and forecasting capabilities12.

QUESTION 50

A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?

Correct Answer: D
A gate review is a type of meeting that evaluates the completion and quality of a project stage and decides whether the project can proceed to the next stage. A gate review is a formal governance step that involves reviewing the goals, progress, risks, deliverables, and benefits of the project, and discussing if the project is still aligned with the business strategy and stakeholder expectations. A gate review can have different outcomes, such as go, kill, hold, recycle, or conditional go, depending on the assessment of the project status and viability123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; Everything Project Managers Need To Know About Gate Reviews | monday.com Blog; Gate reviews: What to do and why you need them - Rebel’s Guide to Project Management; Gates and How to Operate Them - GenSight