QUESTION 26

A project team is comprised of a mix of in-house and virtual team members.
When a complex announcement needs to go out to the entire project team, which of the following is the
MOST effective way to communicate it?

Correct Answer: D
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 260

QUESTION 27

A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:

Correct Answer: C

QUESTION 28

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?

Correct Answer: B

QUESTION 29

Which of the following represents additional unauthorized requirements from the client?

Correct Answer: A

QUESTION 30

Which of the following describes ABurn rate?

Correct Answer: C
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232