A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
Correct Answer:
B
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
Correct Answer:
A
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108
The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.
To alter the pace of the project, which of the following should the project manager do FIRST?
Correct Answer:
C
The project sponsor wishes to implement a 24/7 solution for the service desk, requiring the establishment of the capability on three different continents. Which of the following factors is MOST likely to influence communication methods across the project?
Correct Answer:
B
Which of the following is used to perform a root cause analysis?
Correct Answer:
A
Reference
http://asq.org/learn-about-quality/cause-analysis-tools/overview/overview.html