Universal Containers (UC) has enabled Salesforce Field Service and installed the managed package. UC wants to ensure that Technicians can update their own appointments’ status using the Dispatcher console Gantt chart.
Which steps should the Consultant take to meet these requirements?
Correct Answer:
A
Each container consists of multiple parts that are tracked by Asset records. Universal Containers’s customers usually wait until several parts need service before requesting a Technician come on-site to save money on service charges.
How should a Consultant configure Salesforce Field Service to track the work performed?
Correct Answer:
B
Universal Containers wants to identify which resources need more or fewer appointments. Which Gantt chart filter option should a Consultant recommend to provide this information?
Correct Answer:
D
One of Universal Containers' customers reported that the Technician sent to their site left without cleaning up the work area afterward.
How can Universal Containers ensure that a different Technician is assigned all future work for that Customer?
Correct Answer:
C
An extreme weather situation impacted both the volume of open work and the number of available resources at Universal Containers.
Which approach should a Consultant recommend to realign available resources with open work?
Correct Answer:
B