CSSBB Dumps

CSSBB Free Practice Test

ASQ CSSBB: Certified Six Sigma Black Belt

QUESTION 31

- (Topic 1)
In a series of linked processes and associated feedback loops the product or service flows _____ and the information flows _____ .

Correct Answer: B

QUESTION 32

- (Topic 2)
An x-bar control chart has been established with control limits of 3.245 and 3.257, n = 5. An engineer collects the following sample and plots the average on the control chart: 3.257, 3,256, 3. 258, 3.259

Correct Answer: C

QUESTION 33

- (Topic 1)
A _____ from a sample is used to estimate a population ______. The two words that best fill these blanks are:

Correct Answer: C

QUESTION 34

- (Topic 1)
A medicine with efficacy of .52 is given to five patients. Find the approximate probability that at least one of the patients is cured. (Hint: Use the binomial formula.)

Correct Answer: A

QUESTION 35

- (Topic 2)
In a certain sampling situation, = 0, = 0.08. The power of the sampling plan in this case is:

Correct Answer: D

The formula for power of sampling plan is (1-) = 1-0.08 = 0.92