- (Exam Topic 6)
Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?
Correct Answer:
D
- (Exam Topic 6)
A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
Correct Answer:
B
- (Exam Topic 4)
Managing procurement relationships and monitoring contract performance are part of which process?
Correct Answer:
C
- (Exam Topic 5)
One of the objectives of a quality audit is to:
Correct Answer:
D
- (Exam Topic 6)
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
Correct Answer:
C