CAPM Dumps

CAPM Free Practice Test

PMI CAPM: Certified Associate in Project Management (PMI-100)

QUESTION 21

- (Exam Topic 1)
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Correct Answer: A

QUESTION 22

- (Exam Topic 6)
Match the project life cycle type with its corresponding definition.
CAPM dumps exhibit
Solution:

ADAPTATIVE ITERATIVE PREDICTIVE
INCREMENTAL

Does this meet the goal?

Correct Answer: A

QUESTION 23

- (Exam Topic 2)
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

Correct Answer: A

QUESTION 24

- (Exam Topic 4)
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

Correct Answer: A

QUESTION 25

- (Exam Topic 3)
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Correct Answer: C