- (Exam Topic 1)
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
Correct Answer:
A
- (Exam Topic 6)
Match the project life cycle type with its corresponding definition.
Solution:
ADAPTATIVE ITERATIVE PREDICTIVE
INCREMENTAL
Does this meet the goal?
Correct Answer:
A
- (Exam Topic 2)
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
Correct Answer:
A
- (Exam Topic 4)
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Correct Answer:
A
- (Exam Topic 3)
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Correct Answer:
C