QUESTION 151

- (Topic 3)
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

Correct Answer: C

QUESTION 152

- (Topic 5)
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Correct Answer: A

QUESTION 153

- (Topic 4)
Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Correct Answer: C

QUESTION 154

- (Topic 4)
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

Correct Answer: C

QUESTION 155

- (Topic 4)
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Correct Answer: B