- (Exam Topic 6)
Which two processes should be used to influence costs in the early stages of a project?
Correct Answer:
A
- (Exam Topic 3)
Which enterprise environmental factors are considered during Estimate Costs?
Correct Answer:
A
- (Exam Topic 4)
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Correct Answer:
C
- (Exam Topic 4)
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Correct Answer:
B
- (Exam Topic 6)
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Correct Answer:
B