- (Exam Topic 5)
When cost variance is negative and schedule variance is positive, the project is:
Correct Answer:
B
- (Exam Topic 6)
Why is tailoring in a project necessary?
Correct Answer:
D
Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
- (Exam Topic 2)
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Correct Answer:
D
- (Exam Topic 3)
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
Correct Answer:
C
- (Exam Topic 4)
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
Correct Answer:
B