QUESTION 116

- (Exam Topic 5)
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Correct Answer: D

QUESTION 117

- (Exam Topic 3)
An input of the Plan Procurement Management process is:

Correct Answer: B

QUESTION 118

- (Exam Topic 4)
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Correct Answer: C

QUESTION 119

- (Exam Topic 4)
How is the schedule variance calculated using the earned value technique?

Correct Answer: C

QUESTION 120

- (Exam Topic 3)
What is the term assigned to products or services having the same functional use but different technical characteristics?

Correct Answer: D