- (Exam Topic 6)
Which are examples of processes that may be used once or at predefined points in the project life cycle?
Correct Answer:
A
- (Exam Topic 2)
In the Define Activities process, the schedule management plan is used to:
Correct Answer:
D
- (Exam Topic 6)
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
Correct Answer:
D
- (Exam Topic 3)
Which action should a project manager take to ensure that the project management plan is effective and current?
Correct Answer:
A
- (Exam Topic 2)
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Correct Answer:
D