- (Exam Topic 2)
Project management processes ensure the:
Correct Answer:
D
- (Exam Topic 1)
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is
$50, and the earned value (EV) is $25?
Correct Answer:
C
- (Exam Topic 3)
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
Correct Answer:
C
- (Exam Topic 1)
Which grid shows which resources are tied to work packages?
Correct Answer:
B
- (Exam Topic 6)
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Correct Answer:
D