QUESTION 71

- (Exam Topic 3)
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Correct Answer: C

QUESTION 72

- (Exam Topic 3)
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Correct Answer: C

QUESTION 73

- (Exam Topic 1)
Which tool or technique is used in the Perform Integrated Change Control process?

Correct Answer: D

QUESTION 74

- (Exam Topic 3)
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Correct Answer: D

QUESTION 75

- (Exam Topic 4)
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?