CAPM Dumps

CAPM Free Practice Test

PMI CAPM: Certified Associate in Project Management (PMI-100)

QUESTION 66

- (Exam Topic 2)
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Correct Answer: D

QUESTION 67

- (Exam Topic 1)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Correct Answer: C

QUESTION 68

- (Exam Topic 6)
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

Correct Answer: B

QUESTION 69

- (Exam Topic 1)
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Correct Answer: B

QUESTION 70

- (Exam Topic 6)
In which sphere of influence is the project manager demonstrating the value of project management and advancing the efficacy of the project management office (PMO)?

Correct Answer: B