QUESTION 61

- (Exam Topic 3)
The Verify Scope process is primarily concerned with:

Correct Answer: A

QUESTION 62

- (Exam Topic 3)
Which of the following processes are part of the Project Integration Management Knowledge Area?

Correct Answer: D

QUESTION 63

- (Exam Topic 3)
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

Correct Answer: C

QUESTION 64

- (Exam Topic 6)
What does an S-curve from a Monte Carlo analysis show?

Correct Answer: A

QUESTION 65

- (Exam Topic 4)
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

Correct Answer: D