QUESTION 56

- (Exam Topic 6)
A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

Correct Answer: C

QUESTION 57

- (Exam Topic 6)
When managing costs in an agile environment, what should a project manager consider?

Correct Answer: A

QUESTION 58

- (Exam Topic 1)
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Correct Answer: D

QUESTION 59

- (Exam Topic 4)
What risk technique is used to quantify the probability and impact of risks on project objectives?

Correct Answer: D

QUESTION 60

- (Exam Topic 5)
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Correct Answer: A