QUESTION 31

A company wishes to configure Flow Control for Work Orders. In which application can they change the Start Status and Complete Status that will be used?

Correct Answer: D
The Organizations application is used to configure Flow Control for Work Orders. In this application, you can change the Start Status and Complete Status that will be used.

QUESTION 32

At what database level does a Job Plan exist?

Correct Answer: D
https://maximosecrets.com/2022/04/28/job-plans/

QUESTION 33

Which statement is true regarding Work Assets in the Safety Plans application?

Correct Answer: A
In the Safety Plans application, a Work Asset is either a location or an asset that requires the safety plan. Each safety plan record must have at least one work asset specified, and the work asset can be a location or an asset.

QUESTION 34

Which three coverage options can be included on a contract line in a Warranty Contract? (Choose three.)

Correct Answer: BCF

QUESTION 35

What happens if the Specification of a rotating item is updated in the Item Master application?

Correct Answer: C
It works on both locations and assets. https://maximosecrets.com/2020/08/17/item-and-locations/ and https://maximosecrets.com/2020/08/03/item-specifications-for-rotating-items/